19-04-2010 VENICE People mover (P.le Roma - Tronchetto) 0.857 km 09-08-2010

22-06-2010 BERGEN Bybanen (Byparken - Nesttun)[1] 9.8 km 20-11-2010

27-09-2010 CHENGDU Dujiangyan Line (Chengdu-North Railway Station - Dujinagyan-Qingchengshan) 65 km 29-09-2010
65 | 18.5   1 (Sheixian Lake - Century City) 18.5 km 29-09-2010

27-09-2010 SHENYANG 1 (Shi San Hao Jie - Li Ming Guang Chang) 27.8 km 12-10-2010
49.7   2 (Santaizi - Quanyunlu) 21.9 km 23-01-2012

13-11-2010 MECCA Al Mashaaer Al Mugaddassah Metro (Jamarat (Mina 3) - Arafat Station 1) 18.1 km 01-03-2011

12-03-2011 MASHHAD 1 (Torghaben - Ghadir) 17.965 km 07-08-2011

17-05-2011 RIYAD ? 11.5 km 15-09-2011

19-08-2011 NORFOLK The Tide (EVMC/Fort Norfolk - Newtown Road) 11.9 km 30-08-2011

16-09-2011 XI'AN 2 (Beikezhan - Hizhan Zhogxin) 23.5 km 17-09-2011

20-10-2011 BENGALURU Purple Line (Mahatma Gandhi Road - Baiyappanahalli) 6.7 km 01-11-2011

01-11-2011 ALGIERS 1 (Grande Poste - Hai el Badr) 9.5 km 01-11-2011

01-12-2011 ALMATY 1 (Raymbek Batyr - Alatau) 7.3 km 03-12-2011
28-04-2012 SUZHOU 1 (Mudu - Zhongnan Street) 25 km 12-05-2012

 